Skip to main contentSkip to navigationSkip to footer

PM Case Study: Multi-Phase Fourplex

10 min
5/6

Key Takeaways

  • Phase 2 cost 14% less than Phase 1—learning curve benefit.
  • Portfolio budgeting offset Phase 1 overrun with Phase 2 savings.
  • EVM caught schedule slip for fast-tracking recovery.
  • Risk register correctly predicted highest-impact risk.

Full PM toolkit applied to a multi-phase fourplex renovation.

1

Planning

$220K total (4 units × $55K). Phased: units A&B (weeks 1-12), C&D (weeks 13-24) maintaining 50% occupancy. 120 WBS activities. Risk register identified shared plumbing as highest risk.

2

Execution

Phase 1 on track through week 6 (SPI 1.02). Week 7: shared drain stacks require replacement—$10,800 CO (identified risk materialized). SPI recovered to 0.97 via fast-tracking. Phase 1 completed week 13 at $59,200/unit. Phase 2 benefited from lessons: $50,800/unit, on time.

3

Results

25 weeks total (+1), exactly on $220K budget (Phase 2 under-run offset Phase 1 over-run). Rent increased $400/unit.

MetricPhase 1Phase 2Total
Duration13 wk (+1)12 wk25 wk (+1)
Cost/Unit$59,200$50,800$55,000 avg
SPI0.921.000.96
CPI0.931.081.00

Multi-phase results

Key Takeaways

  • Phase 2 cost 14% less than Phase 1—learning curve benefit.
  • Portfolio budgeting offset Phase 1 overrun with Phase 2 savings.
  • EVM caught schedule slip for fast-tracking recovery.
  • Risk register correctly predicted highest-impact risk.

Common Mistakes to Avoid

Trying to renovate all units simultaneously without staggered scheduling

Consequence: Trade crews wait for each other, inspections bottle up, and the project takes longer than sequential renovation

Correction: Stagger unit starts by 1-2 weeks so crews flow sequentially through units with minimal downtime

Test Your Knowledge

1.What is the biggest project management challenge in multi-unit renovation projects?

2.What scheduling technique works best for multi-unit renovation?