Key Takeaways
- EVM needs three baselines: PMB, WBS budgets, and completion measurement.
- Weekly SPI/CPI/EAC provides objective health in simple numbers.
- Traffic lights (green/yellow/red) trigger management responses.
- TCPI >1.1 means budget unlikely without scope reduction.
Practical EVM implementation for residential renovation projects.
EVM Setup
Requires: Performance Measurement Baseline (budget spread over timeline), WBS with budget assignments, consistent completion measurement method.
Weekly Analysis
Calculate PV, EV, AC weekly. Derive SPI, CPI, EAC. Traffic light: green (≥0.95), yellow (0.85-0.95), red (<0.85).
Interpreting Results
SPI<1 + CPI≥1: behind schedule, on budget—focus on schedule recovery. SPI≥1 + CPI<1: on time, over budget—investigate costs. Both <1: comprehensive review needed. TCPI>1.1: original budget unlikely without scope reduction.
Case Study: Midpoint EVM Analysis
Week 7 of 14, $90K budget.
- 1PV = $90K × 55% = $49,500.
- 2EV = $90K × 50% = $45,000 (50% complete).
- 3AC = $48,000.
- 4SPI = 0.909 (yellow). CPI = 0.938 (yellow).
- 5EAC = $90K/0.938 = $95,948.
- 6Action: recovery meeting, confirm contingency covers $5,948 projected overrun.
Dual issue detected at midpoint with recovery options available.
Key Takeaways
- ✓EVM needs three baselines: PMB, WBS budgets, and completion measurement.
- ✓Weekly SPI/CPI/EAC provides objective health in simple numbers.
- ✓Traffic lights (green/yellow/red) trigger management responses.
- ✓TCPI >1.1 means budget unlikely without scope reduction.
Sources
- PMI Earned Value Management Practice Standard(2025-01-15)
- NAHB Construction Financial Management Guide(2025-01-15)
Common Mistakes to Avoid
Ignoring EVM warning signs until the budget is significantly overrun
Consequence: By the time CPI drops below 0.90, recovery typically requires scope reduction or additional capital injection
Correction: Review EVM metrics weekly; initiate corrective action when CPI drops below 0.95 or SPI drops below 0.90
Test Your Knowledge
1.What does a Cost Performance Index (CPI) of 0.85 mean?
2.What EVM metric predicts the final project cost?