Skip to main contentSkip to navigationSkip to footer

Change Management Decision Frameworks

10 min
3/6

Key Takeaways

  • Evaluate necessity, ROI, schedule impact, cumulative effect, deferability.
  • Seven-step process: no work before signed CO.
  • Thresholds at 5%, 10%, 15% trigger escalating reviews.
  • Track changes as dollars and percentage of contract.

Decision frameworks for evaluating and controlling change orders.

1

Change Evaluation Matrix

Evaluate: Necessary for safety/code? Increases value > cost? Affects critical path? Cumulative approaching 10%? Can be deferred?

2

Seven-Step Change Control

Request → Impact Analysis → Evaluation → Negotiation → Decision → Signed CO → Budget/Schedule Update. No work before step 6.

3

Cumulative Thresholds

At 5%: review remaining scope for potential changes. At 10%: full project feasibility review. At 15%: evaluate if minimum returns achievable.

Case Study: Evaluating Three COs

Week 6 of $85K renovation, three COs totaling $7,200.

  1. 1CO1 $2,400 subfloor rot: necessary, approve.
  2. 2CO2 $3,200 quartz upgrade: positive ROI but 1-week delay. Defer.
  3. 3CO3 $1,600 recessed lights: not necessary, no schedule impact. Negotiate to $1,200, approve.
  4. 4Cumulative: $3,600 (4.2%). Below 5% threshold.
Outcome

Structured evaluation approves necessary items, defers delays, negotiates discretionary work.

Key Takeaways

  • Evaluate necessity, ROI, schedule impact, cumulative effect, deferability.
  • Seven-step process: no work before signed CO.
  • Thresholds at 5%, 10%, 15% trigger escalating reviews.
  • Track changes as dollars and percentage of contract.

Common Mistakes to Avoid

Approving investor-requested upgrades without analyzing the ROI impact

Consequence: Spending $5,000 on an upgrade that adds only $2,000 in value, reducing overall project profitability

Correction: Run every investor-requested change through the ROI filter: will this change add more value than it costs?

Test Your Knowledge

1.What framework helps decide whether to approve a change order?

2.What percentage of change order costs typically come from hidden conditions vs. investor-requested changes?