Skip to main contentSkip to navigationSkip to footer

Contract Types and Structuring

8 min
3/6

Key Takeaways

  • Fixed-price places cost risk on contractor for defined scopes.
  • Cost-plus provides transparency for uncertain scopes.
  • T&M suits small or emergency work only.
  • Essential terms include draw schedule, CO process, retainage, and warranty.

Different contract types allocate risk differently between investor and contractor.

Process Flow

1

Three Contract Types

Fixed-Price: contractor bears cost overrun risk, best for defined scopes. Cost-Plus: investor bears risk but gains transparency. T&M: open-ended exposure, suit small/emergency work only.

TypeRisk BearerBest For
Fixed-PriceContractorDefined scope, competitive bidding
Cost-PlusInvestorUncertain scope, trusted relationships
T&MInvestorSmall scope, emergency repairs

Contract type risk allocation

Loading interactive chart...
2

Essential Contract Terms

Every contract must include: SOW, price, draw schedule, timeline, change order process, insurance requirements, warranty (1-2 years), dispute resolution, termination provisions, and lien waiver requirements.

3

Negotiation Priorities

Priority order: draw schedule structure, change order process, retainage, warranty, insurance/indemnification, dispute resolution. Use standard templates (AIA A101 or custom) rather than accepting contractor-provided contracts.

Key Takeaways

  • Fixed-price places cost risk on contractor for defined scopes.
  • Cost-plus provides transparency for uncertain scopes.
  • T&M suits small or emergency work only.
  • Essential terms include draw schedule, CO process, retainage, and warranty.

Common Mistakes to Avoid

Using time-and-materials contracts for defined renovation scopes

Consequence: No cost ceiling; contractor has no incentive to work efficiently and costs can exceed budget by 30-50%

Correction: Use fixed-price contracts for defined scopes; reserve T&M only for genuinely undefined exploratory work

Not including a change order process in the contract

Consequence: Contractor performs additional work and presents bills after the fact with no pre-approval or price negotiation

Correction: Include a formal change order clause requiring written approval before any scope additions, with cost and schedule impact documented

Test Your Knowledge

1.Which contract type gives the investor the most cost certainty?

2.What is the recommended retainage percentage for residential renovations?

3.What contract clause protects against contractor schedule delays?