Skip to main contentSkip to navigationSkip to footer

Draw Schedules and Payment Management

10 min
4/6

Key Takeaways

  • Draw schedules: milestone-based, back-loaded, inspection-verified.
  • Standard 5-draw schedule covers major construction phases.
  • Verify every draw with site visit and lien waivers.
  • Retainage 5-10% provides punch list leverage.

Draw schedules align payments with completion, protecting investor capital.

1

Draw Schedule Design

Standard 5-draw: Demo 15%, Framing 20%, Rough MEP/Drywall 25%, Finishes 25%, Final 15%. Each draw lags completion. Never pay ahead.

DrawMilestone%Cumulative
1Demo complete15%15%
2Framing complete20%35%
3MEP/Drywall25%60%
4Finishes25%85%
5Final/CO15%100%

Standard 5-draw schedule

2

Draw Verification

Site visit, inspection confirmation, lien waiver collection, budget reconciliation before every payment.

3

Retainage System

Withhold 5-10% from each draw. Release only after all work complete, punch list resolved, CO issued, and lien waivers collected.

Guided Practice: Managing Draws: $90K Renovation

Five draws with 10% retainage.

  1. 1Each draw: verify milestone, withhold 10%, collect previous waivers.
  2. 2Final: confirm CO + punch list, release all retainage.
  3. 3Total paid: $90,000 in five verified installments.

Key Takeaways

  • Draw schedules: milestone-based, back-loaded, inspection-verified.
  • Standard 5-draw schedule covers major construction phases.
  • Verify every draw with site visit and lien waivers.
  • Retainage 5-10% provides punch list leverage.

Common Mistakes to Avoid

Paying ahead of verified work completion

Consequence: Loss of leverage if contractor underperforms, abandons project, or goes bankrupt

Correction: Never pay ahead—tie every draw to verified milestone completion with site visit confirmation

Not collecting lien waivers at every draw

Consequence: Unpaid subcontractors can file mechanics liens on your property even if you paid the GC in full

Correction: Collect conditional lien waivers with draw requests and unconditional waivers with each payment

Test Your Knowledge

1.What is the standard number of draws for a residential renovation?

2.What must be collected before approving any draw payment?

3.What is the purpose of retainage?