Developing a Walkthrough Estimate

10 min
2/6

Key Takeaways

  • Start exterior—often the highest-cost elements.
  • Interior follows system hierarchy: MEP then finishes.
  • Reference table of 20-30 items enables rapid estimation.
  • Add GC overhead, contingency, and soft costs to subtotal.

The step-by-step walkthrough estimation process with mental math shortcuts.

1

Exterior Estimating

Roof (squares × $400-$700), windows (count × $400-$800), foundation ($5K-$15K if cracked), siding (area × $3-$15/SF).

2

Interior Estimating

Panel ($2K-$4.5K), HVAC ($5K-$12K), kitchen minor ($15K-$30K), bathroom ($12K-$25K each), flooring ($3-$15/SF), paint ($2-$4.50/SF).

ItemMethodRange
RoofSquares × $400-$700$8K-$25K
HVACTons × $2.5K-$4.5K$5K-$12K
Kitchen minorLF × $200-$300$15K-$30K
Bathroom midEach$12K-$25K
Flooring LVPSF × $5-$10$4K-$15K

Quick estimation reference

3

Assembling the Estimate

Sum line items + General Conditions (5-8%) + Contingency (10-20%) + Soft Costs (3-8%) = Total Renovation Budget.

Guided Practice: Walkthrough Estimate: 1,800 SF Colonial

Touring a 1975 colonial listed at $180K with $290K ARV.

  1. 1Exterior: roof $11K, windows $8.4K.
  2. 2MEP: panel $3.5K, HVAC $9K, water heater $1.8K.
  3. 3Kitchen $21.2K, baths (2) $36K.
  4. 4Flooring $9.8K, paint $5.4K, trim $3.5K.
  5. 5Total with markups: $138,623.
  6. 670% Rule: $203K - $138.6K = $64.4K max offer. Pass.

Key Takeaways

  • Start exterior—often the highest-cost elements.
  • Interior follows system hierarchy: MEP then finishes.
  • Reference table of 20-30 items enables rapid estimation.
  • Add GC overhead, contingency, and soft costs to subtotal.

Common Mistakes to Avoid

Focusing interior estimate on finishes while neglecting MEP assessment

Consequence: Missing a $9,000 HVAC replacement or $3,500 panel upgrade that dramatically changes the budget

Correction: Follow system hierarchy during walkthrough: MEP systems first, then finishes

Not applying the 70% Rule as a screening check

Consequence: Proceeding with detailed analysis on properties that fail basic profitability screening

Correction: Calculate max offer using 70% Rule before investing time in detailed estimation

Test Your Knowledge

1.Where should walkthrough estimating begin?

2.What is the correct order of cost additions to arrive at total renovation budget?

3.In the case study, what was the correct acquisition decision?